Construction Schedule
  • Phase 1 - Fencing
  • Phase 2 - Layout
  • Phase 3 - Excavation
  • Phase 4 - Plumbing and Equipment Set
  • Phase 5 - Steel
  • Phase 6 - Electric
  • Phase 7 - City Inspection
  • Phase 8 - Shotcrete
  • Phase 9 - Waterfall and Boulder Set
  • Phase 10 - Decking
  • Phase 11 - Tile
  • Phase 12 - Clean-Up
  • Phase 13 - Fencing
  • Phase 14 - Pre-Plaster Inspection
  • Phase 15 - Interior Finish
  • Phase 16 - Start-Up
If fence removal is done by Taylor Made Pools & Spas, LLC, it will be scheduled at the time of excavation. If removal is through you, please notify us upon completion so that the excavation can be scheduled.